Maintaining the Material Master for Parallel Discontinuation (Main Material) 

  1. Call up the transaction as follows:
  2. Menu Path

    From the Production node, choose Master Data ® Material Master ® Material ® Change ® Immediately.

    Transaction Code

    MM02

  3. Enter the following data:
  4. Field

    Data

    Material

    400-510

  5. Choose .
  6. There are different ways to get to the MRP 4 screen. For more information, refer to the relevant SAP Library documentation.

  7. In the dialog box, select MRP 4.
  8. Choose .
  9. Enter the following data:
  10. Field

    Data

    Plant

    1000

  11. Choose .
  12. To make sure that no discontinuation has been prepared, check the following data:
  13. Field

    Data

    Discontin. ind.

    1

    Eff.-out date

    1st of the next month

    Follow-up mat.

    400-520

  14. Choose .
  15. The system confirms that changes have been made to the material.

  16. Remain on this screen.