Requirements Run for Long-Term Planning 

  1. Call up the transaction as follows:
  2. Menu Path

    From the Long-Term Planning node, choose Long-Term Planning ® Single-Item, Multi-Level

    Transaction Code

    MS02

  3. Enter the following data:
  4. Field

    Data

    Plnng scenario

    Your number

    Material

    P-400

    Plant

    1000

    Processing key

    NETCH

    Create MRP list

    1

    Planning mode

    3

    Scheduling

    2

    Also plan unchanged components

    Select

    Display material list

    Select

  5. Choose .
  6. To skip the information message, simply choose .
  7. Choose Materials.
  8. Select the first item in the list (independent requirement).
  9. Choose Selected results.
  10. You see the planning results based on the planned orders generated during MRP for the finished product.

  11. Choose .
  12. Also check the other materials.

  13. Choose until the overview tree appears.
  14. Compare the planning result of the long-term planning with the result of the current planning requirement.

  15. Call up the next transaction as follows:
  16. Menu Path

    From the Production node, choose MRP ® Evaluations ® Stock/Reqmts List

    Transaction Code

    MD04

  17. Enter the following data:
  18. Field

    Data

    Material

    P-400

    Plant

    1000

  19. Choose .
  20. Choose until the overview tree appears.