Converting the Planned Order into a Production Order 

  1. Call up the transaction as follows:
  2. Menu Path

    From the MRP node, choose Evaluations ® Stock/Requirements List

    Transaction Code

    MD04

  3. Enter the following data:
  4. Field

    Europe

    North America

    Material

    HD-1300

    HD-1300

    Plant

    1000

    3000

  5. Choose .
  6. Choose for your planned order.
  7. In the dialog box, choose -> Prod. order (Convert planned order into production order).
  8. If a dialog box should appear, choose .

  9. Choose .
  10. You see the material components.

  11. Choose .
  12. Choose .
  13. You now see the operations.

  14. Make a note of the final operation in the list.
  15. Choose .
  16. To release the order, choose .
  17. The system informs you that the release has been carried out.

  18. To display the operation scheduling overview, choose Goto ® Graphic ® Gantt chart.
  19. Choose and Yes to return to the Production Order Create: Header screen.
  20. To display the current order status, choose .
  21. Choose .
  22. Choose .
  23. The system informs you that scheduling has been carried out.

  24. Choose .
  25. Make a note of this production order number.
  26. Choose .
  27. You see that the planned order has now been converted into a production order.

  28. Choose until the overview tree appears.