Displaying Consumption in the Stock/Requirements List 

  1. Call up the transaction as follows:
  2. Menu Path

    From the Production node, choose MRP ® Evaluations ® Stock/Requirements List

    Transaction Code

    MD04

  3. Enter the following data:
  4. Field

    Data

    Material

    P-101

    Plant

    1000

  5. Choose .
  6. On the Stock/Requirements List as of ## Hrs you see that the production order is no longer relevant for requirements planning, because the confirmed quantity has been entered in the plant stock.

  7. Choose .