Planning a Product with Final Assembly 

  1. Call up the transaction as follows:
  2. Menu Path

    Logistics ® Production ® Production Planning ® Demand Management ® Planned Independent Requirements ® Change

    Transaction Code

    MD62

  3. Enter the following data:
  4. Field

    Europe

    North America

    Material

    P-100

    P-100

    Plant

    1000

    3000

  5. Choose Reqmts parameters and enter the following data in the dialog box:
  6. Field

    Europe

    North America

    Plant

    1000

    3000

    Requirements type

    VSF

    VSF

    Version

    00

    00

    Period split

    Select

    Select

    Active

    Select

    Select

    Item screen

    Select

    Select

    History indicator

    Select

    Select

  7. Choose .
  8. To skip any information messages, choose .

    The Change Planned Independent Requirements: Initial Screen appears.

  9. Choose .
  10. Select the item and choose the Sched. lines tab.
  11. You now make entries for the next month, and for the following six months:
  12. Field

    Europe

    North America

    (P) Period indicator

    M

    M

    Reqmts dt.

    Relevant month

    Relevant month

    Planned qty

    100 (for each month)

    100 (for each month)

  13. Choose .
  14. To check the current warehouse stock, choose Environment ® Stock reqmts/list.

    Choose .

  15. Choose .
  16. Choose until the overview tree appears.