Case 1
A global company may have materials that are maintained in many locations within the same system. Each month the previous posting period is closed and a new posting period is opened. The period close program requires that no changes be made to material records – including goods movements. Since a period close program in the evening in one location may conflict with goods movements during the day in another, a workable procedure for this transaction must be developed.
Case 2
There can also be problems when the local posting date is not in an open period or it is posted in the previous period when it should probably be posted in the current period.
Either case may occur when time zone differences exist between the central period close location and distributed plant locations.
Process Flow
Case 1
Case 2
Tips
See also