Posting the Goods Receipt for the Production Lot 
Procedure
The Goods receipt for production lot screen appears.
Posting Date
Using this date, the system determines the current BOM if you have not specified an additional revision level.
Document date
The current day’s date is suggested as the document date. Check the date.
Plant
Enter the plant for which you would like to carry out the goods receipt for the production lot.
Production lot
The planned order appears in the appropriate field and the planned order quantity is suggested as the backflush quantity.
You choose: Edit ® Actual data, in order, for example, to check the data of the components or enter actual times. (See also:
Entering Actual Times ).You choose Goto ® Change parameters in order to, for example, post ordering costs or to post the goods receipt in another type of stock.