The following example shows a substitution rule for changing the cost center in the asset master record. The cost center should be changed for all assets in the asset class 1000 as of 1/1/1996 from "QKI" to "1", if "QKI" is the valid cost center after 12/31/1995:
Precondition:
ANLA - ANLKL = '00001000' and
ANLZ - KOSTL = 'QKI ' and
ANLZ $BDATU > '19951231'
Substitution (when the condition is fulfilled):
Cost center: 1
Valid from: 01/01/96
Note that the Valid to date (BDATU) in the condition has to be entered in the year/month/day form.