Maintaining Reference Points in the Bill of Material Item 

 

Prerequisites

You have defined reference points in Customizing the Project System under Material ® BOM transfer.

Procedure

  1. Choose Logistics® Production ® Master data ® Bills of material ®Bill of material ® Material BOM, Order BOM, or WBS BOM® Create or Change.
  2. Enter the relevant data on the initial screen and choose .
  3. The item overview appears.

  4. Go to the detail screen of the item by double-clicking on the relevant item number.
  5. Enter a reference point in the Basic data tab page. You can only enter reference points that have been defined in Customizing for the Project System.
  6. Save the BOM.