Editing Material Assignments in Standard Networks 

Use

Use this procedure to display material assignments to standard networks and to edit the assigned BOM.

Procedure

  1. There are the following options for displaying and editing assignments to standard networks.

- To display all assignments for a standard network, on the header or in the activity overview choose Goto ® Comp.overview netwk.

The Change Standard Network: Material Assignment screen appears, on which all BOM components are listed. If a component is assigned to an activity, the activity number is listed in one of the columns.

- To display the assignments for individual activities, select the relevant activities in the activity overview and choose Activity ® Component overview.

The Change Standard Network: Material Assignment screen appears with all the components for the activity. If you have selected several activities, you can move between the individual activities by using the arrow buttons.

To access the detail screen for a component from one of these overviews, select the component and choose Details ® Component ® General or Administrative data.

  1. To reassign components, select the components on the Change Standard Network: Material Assignment screen and choose Edit ® Reassign.
  2. A dialog box appears in which you can enter an activity to reassign the component or you call up a list of activities and select one. To assign the component to this activity, choose Choose.

  3. To delete assignments, select the components on the Change Standard Network: Material Assignment screen and choose Edit ® Delete.
  4. When you confirm the deletion, the assignment of the material component to the activity is deleted. The system still displays the component in the component overview for the standard network.

  5. To assign BOM components that have not yet been assigned or to additionally assign a component to another component, select the components and choose Edit ® Reassign. This function is only available on the component overview for the whole standard network.
  6. To edit the assigned BOM, in the component overview choose Goto ® Bill of Material ® Edit BOM.

The BOM item overview appears. You can now change or delete BOM items or create new BOM items.

When you return to the component overview, the changes are displayed. If you are in the component overview for an activity, all new BOM items are automatically assigned to the activity.