Assigning Material Components to Standard Networks 

  1. Choose Logistics or Accounting ® Project System ® Basic data ® Standard templates ® Standard network ® Change.
  2. You can also assign material to a standard network when you create the standard network.

  3. Enter a standard network and choose Activities.
  4. Select the required activities in the activity overview and choose Activities ® Component overview or choose Goto ® Comp.Overview Netwk.

If no material components have been assigned to the standard network yet, the Bill of Material dialog box appears.

If material components have already been assigned to activities of the standard network, a dialog box appears in which the corresponding BOMs are displayed.

The further procedure is the same as if no components had been assigned.

  1. You assign material components as follows:

If several BOM alternatives exist for the material, a dialog box with the alternatives appears. Select an alternative. A list of the material assignments appears.

  1. Select the BOM items that you want to assign and choose Edit ® New assignment.
  2. In the New Assignment dialog box, enter an activity or choose Oper/act. list to display a list of all the activities. Select an activity from the activity list.
  3. The system assigns the BOM items to the activity.

  4. If necessary repeat the last step to assign further BOM items to other activities.
  5. Choose Back.
  6. The activity overview appears again.

  7. Save the standard network.