Distributing Work in the Work Center View 

  1. Choose Logistics or Accounting ® Project System ® Resources ® Workforce planning® Work center view.
  2. Enter a work center, plant, personnel resource, or a range for one of these items on the Work center selection screen.
  3. To further restrict the selection of activities, enter a network, activity, or a range in the Filter section of the screen.
  4. Enter a profile and choose (Enter) to use its settings.
  5. If necessary, change the planning period, or the other settings by choosing .
  6. Choose .

The work center view of workforce planning appears.

The personnel resources that meet the selection criteria are listed in the top part of the screen, the "planning section".

In the lower section is the "worklist, a list of all the activities (that fit the filter criteria) which are processed at the selected work center.

  1. Select the activities and the personnel resources that you want to assign, and choose .

The system assigns the selected activities to the relevant personnel resources and lists the activities under the names of these resources. In the rows for the activities those periods are available for entry that are within the scheduled latest dates for the activities.

  1. Place the cursor on such a period and enter the work the personnel resource should carry out for the activity in this period. The unit for work, which is taken from the labor capacity of the work center, is in the column before the periods.
  2. Save the work distribution by choosing .

There are additional functions in the work center view of workforce planning. See Functions in the Work Center View.