PS-EPS: Attributes for Network Activities 
Object Methods Without Attributes
The following object methods apply to network activities. You do not have to specify any attributes (fields) to delete or release network activities or prevent them from being scheduled:
Object Methods With Attributes
Select from the following table the attributes (fields) in network activities to be used in either
ATTRIBUTES or ATTRIBUTE_LINES with the following object methods:The attributes of these methods are the same as the fields in the ABAP/4 dictionary structures
IFNETACTEX and IFNETACTIM .The object method for confirming network activities has its own attributes:
For detailed information on the attribute type refer to
Data Formats of Attributes in Object Methods.Attribute |
Required Field |
Type |
Length |
Description |
Method |
AUFNR |
CHAR |
12 |
Order/Network number |
X | |
VORNR |
CHAR |
4 |
Activity number |
X | |
STEUS |
Ö |
CHAR |
4 |
Control key |
X |
ARBPL |
Ö |
CHAR |
8 |
Work center |
X |
WERKS |
Ö |
CHAR |
4 |
Plant |
X |
LTXA1 |
TEXT |
40 |
First line of the activity description |
X | |
LIFNR |
Ö |
CHAR |
10 |
Vendor (creditor) account number |
X |
PREIS |
CURR |
11 |
Price |
X | |
PEINH |
DEC |
5 |
Price unit |
X | |
SAKTO |
Ö |
CHAR |
10 |
Cost element |
X |
WAERS |
Ö |
CUKY |
5 |
Currency key |
X |
INFNR |
Ö |
CHAR |
10 |
Purchasing information record number |
X |
EKORG |
Ö |
CHAR |
4 |
Purchasing organization |
X |
EKGRP |
Ö |
CHAR |
3 |
Purchasing group for the external processing |
X |
MATKL |
Ö |
CHAR |
9 |
Material group |
X |
DDEHN |
CHAR |
1 |
Indicator: flexible duration |
X | |
ANZZL |
INT1 |
3 |
Number of capacities required |
X | |
PRZNT |
INT1 |
3 |
Work percentage |
X | |
MLSTN |
Ö |
CHAR |
5 |
Usage |
X |
LARNT |
CHAR |
6 |
Activity type |
X | |
PRKST |
CURR |
11 |
Costs in the activity |
X | |
RUECK |
NUMC |
10 |
Confirmation number of activity |
R | |
RMZHL |
NUMC |
8 |
Internal counter |
R | |
PSPID |
Ö |
CHAR |
24 |
Project definition |
X |
POSID |
Ö |
CHAR |
24 |
Work breakdown structure element (WBS element) |
X |
BANFN |
CHAR |
10 |
Purchase requisition number |
R | |
BNFPO |
NUMC |
5 |
Item number of the purchase requisition in the network |
R | |
KALID |
CHAR |
2 |
Factory calendar ID |
X | |
VERTL |
Ö |
CHAR |
8 |
Key for distributing capacity requirements for other types of internal processing (networks) |
X |
NPRIO |
Ö |
CHAR |
1 |
Priority |
X |
TXJCD |
Ö |
CHAR |
15 |
Jurisdiction for tax calculation - tax jurisdiction code |
X |
SCOPE |
Ö |
CHAR |
2 |
Object class |
X |
GSBER |
Ö |
CHAR |
4 |
Business area |
R |
PRCTR |
Ö |
CHAR |
10 |
Profit center |
X |
NO_DISP |
CHAR |
1 |
Indicator: Reservation. not applicable to MRP; purchase requisition not created |
X | |
CLASF |
CHAR |
1 |
Indicator: Activity taken into account for project summarization |
X | |
MEINH |
Ö |
UNIT |
3 |
Unit of measure for activity |
X |
PLIFZ |
DEC |
3 |
Planned delivery time in days |
X | |
DAUNO |
QUAN |
5 |
Normal duration of the activity |
X | |
DAUNE |
UNIT |
3 |
Unit for normal duration |
X | |
DAUMI |
QUAN |
5 |
Minimum activity duration |
X | |
DAUME |
UNIT |
3 |
Unit for the minimum duration |
X | |
EINSA |
CHAR |
1 |
Constraint on the basic start date for the activity |
X | |
EINSE |
CHAR |
1 |
Constraint on the finish date for the activity |
X | |
ARBEI |
QUAN |
7 |
Work involved in the activity |
X | |
ARBEH |
UNIT |
3 |
Unit for work |
X | |
ISMNW |
QUAN |
7 |
Actual work |
R | |
FSAVD |
DATS |
8 |
Earliest scheduled start: Execution (date) |
X | |
FSAVZ |
TIMS |
6 |
Earliest scheduled start (time) |
X | |
FSEDD |
DATS |
8 |
Earliest scheduled finish (date) |
X | |
FSEDZ |
TIMS |
6 |
Earliest scheduled finish (time) |
X | |
SSAVD |
DATS |
8 |
Latest scheduled start (date) |
X | |
SSAVZ |
TIMS |
6 |
Latest scheduled start(time) |
X | |
SSEDD |
DATS |
8 |
Latest scheduled finish (date) |
R | |
SSEDZ |
TIMS |
6 |
Latest scheduled finish (time) |
X | |
ISDD |
DATS |
8 |
Actual start (date) |
R | |
ISDZ |
TIMS |
6 |
Actual start (time) |
R | |
IEDD |
DATS |
8 |
Actual finish (date) |
R | |
IEDZ |
TIMS |
6 |
Actual finish (time) |
R | |
PEDD |
DATS |
8 |
Forecast finish date of activity from confirmation |
R | |
PEDZ |
TIMS |
6 |
Forecast finish time of activity from confirmation |
R | |
PUFFR |
DEC |
3 |
Free float |
X | |
PUFGS |
DEC |
3 |
Total float |
X | |
NTANF |
DATS |
8 |
Constraint for activity start (Basic) |
X | |
NTANZ |
TIMS |
6 |
Constraint for activity start time (Basic) |
X | |
NTEND |
DATS |
8 |
Constraint for finish of activity (Basic) |
X | |
NTENZ |
TIMS |
6 |
Basic finish time of the activity |
X | |
DABEA |
QUAN |
7 |
Processing time |
R | |
BEAZE |
UNIT |
3 |
Unit of measure for processing time |
R | |
OFMNW |
QUAN |
7 |
Forecast work (actual + remaining) |
R | |
PDAU |
QUAN |
5 |
Forecast duration of activity from confirmation |
R | |
PDAE |
UNIT |
3 |
Unit of the forecast duration from the confirmation |
R | |
SLWID |
CHAR |
7 |
Key word ID for user-defined fields |
X | |
USR00 |
CHAR |
20 |
User-defined field with 20 characters |
X | |
USR01 |
CHAR |
20 |
User-defined field with 20 characters |
X | |
USR02 |
CHAR |
10 |
User-defined field with 10 characters |
X | |
USR03 |
CHAR |
10 |
User-defined field with 10 characters |
X | |
USR04 |
QUAN |
13 |
User-defined field for quantity with length 10.3 |
X | |
USE04 |
UNIT |
3 |
User-defined field: Unit for quantity fields |
X | |
USR05 |
QUAN |
13 |
User-defined field for quantity with length 10.3 |
X | |
USE05 |
UNIT |
3 |
User-defined field: Unit for quantity fields |
X | |
USR06 |
CURR |
13 |
User-defined field for values with length 10.3 |
X | |
USE06 |
CUKY |
5 |
User-defined field: Unit for value fields |
X | |
USR07 |
CURR |
13 |
User-defined field for values with length 10.3 |
X | |
USE07 |
CUKY |
5 |
User-defined field: Unit for value fields |
X | |
USR08 |
DATS |
8 |
User-defined field for date |
X | |
USR09 |
DATS |
8 |
User-defined field for date |
X | |
USR10 |
CHAR |
1 |
User-defined field: Indicator for reports |
X | |
USR11 |
CHAR |
1 |
User-defined field: Indicator for reports |
X | |
IDAUR |
QUAN |
5 |
Actual duration for confirmation |
R | |
IDAUE |
UNIT |
3 |
Unit for actual duration |
R | |
ODAUR |
QUAN |
5 |
Remaining duration for activity |
R | |
ODAUE |
UNIT |
3 |
Unit for remaining duration |
R | |
STATXT |
CHAR |
40 |
Edited status text |
R | |
LOEKZ |
CHAR |
1 |
Indicator: Activity is deleted |
R |