Copying Views 

Use

You can display various values next to planning values in the WBS element overview and the annual overview. You can use part of the view that you set up as a planning value, or you can add it to existing planning values.

Procedure

  1. Choose Views to select the view that you wish to take as a planning value or add to existing values.
  2. Select the WBS elements that you wish to copy the selected view to.
  3. Choose Edit -> Copy view
    Enter the percentage of the view that is set up, then choose whether this value should overwrite the existing value or be added to it.
  4. Choose Continue.
    According to the percentage that you chose, the system takes the values from the installed view as planning values or adds them to existing planning values. It does this for the selected WBS elements.
    You can adapt the values by overwriting.
  5. Save the planning values by choosing Planning values -> Save without checks.