Menu Path |
Logistics ® Production ® Production Planning ® Demand Management ® Planned Independent Requirements ® Create |
Transaction Code |
MD61 |
Field |
Data |
Material |
P-103 |
Plant |
3000 |
Version |
00 |
Field |
Data |
Plant |
3000 |
Requirements type |
LSF |
Version |
00 |
Period ind. (= period indicator) |
W |
Display |
Period split |
Active |
Select |
Overview |
Item screen |
History indicator |
Select |
The Planned Independent Requirements: Overview screen appears.
Fields |
Data |
P (= period indicator) |
W |
Reqmts dt. |
One of the following weeks |
Planned qty |
50 (per week) |
If required, you can now modify the automatic splitting. If you do make any changes, for example, to the quantity or date, you may need to confirm a system message after saving your data with Yes. To skip any warning messages, choose
.