Make-to-Order Without Assembly Processing  

If the make-to-order items are not to be assembled till a later point in time and, therefore, the availability situation at the time of order entry is not so critical, you can perform make-to-order without using assembly processing.

In this case, the availability check, delivery date determination and costing are all performed after order entry.

Using a Project Without Assembly Processing

If you do not need accurate information on material availability, schedules or costs at the time you create a sales order, you do not have to use assembly processing to use the Project System.

You can still assign a sales order, such as a sales order, when you create a network. The following applies:

In this case, the system automatically creates the settlement rules for the network.

See also:

For more information on sales orders and how to assign sales orders to a WBS element, refer to the SAP documentation SD Sales and Distribution, Section Sales: Working with Special Business Processes: Make-to-order Processing.