Assemble-to-order with Projects
Use networks and projects for assemble-to-order if you manufacture or engineer your products to order and you are not sure exactly how you are going to execute the sales order:
You can still use planned orders and production orders if you choose to create a network from a sales order.
Account Assignment
In assemble-to-order with projects you can choose where the costs are collected: for example, in a work breakdown structure element (WBS element), in the sales order, or in the network.
Network is... |
Account assignment is made to... |
The standard WBS element from the standard network header... |
header-assigned |
sales order |
is not copied into the network header |
activity-assigned |
project |
is copied into the network header as a WBS element. If no standard WBS element has been entered in the standard network header, you have to specify a WBS element when you save. |
header-assigned |
project |
is copied into the network header as a WBS element. If no standard WBS element has been entered in the standard network header, you have to specify a WBS element when you save. |
It is not possible to assign an network with activity account assignment to a sales order.