Calling Up Reports on Progress Analysis 
Use
This report offers a structure-oriented overview of the POC and earned value figures. It shows the values in total and by period. You can branch directly from the period breakdown to the graphical value display.
Prerequisite
You have determined the progress relating to a progress version.
Procedure
The system may ask you to enter a PS info profile.
The system may ask you to enter a controlling area.
This brings you to the screen Project Info System: Progress Analysis Initial Screen.
The Plan Versions dialog box appears.
To be able to analyze costs from the CO versions in the structure overview together with the progress values, you must, when accessing the report, specify the appropriate CO version (such as a forecast version) as plan version 2.
. Result
The report shows the progress analysis values in line with the project hierarchy. Use the
field selection to choose further fields for evaluation. In the overview, you can display both time-dependent values, such as the planned POC, and time-independent values, such as the method assigned to the project component. Choose Goto ® Period breakdown to display the time-dependent values for a project component.
If you do not want to display cumulative values, choose Settings
® Value display ® Not cumulated. The system displays the values in the period in which they occur, and inserts a totals line.
Values determined in the current period are shown in the period breakdown only.
Graphical Representation
From the period breakdown, choose Goto
® Graphic ® Period breakdown to access the graphical overview of the time-dependent values.
Use
Select fields in the period breakdown to select the fields you want displayed in the graphic.