Set up
Availability Control Again
In this IMG activity, you reconstruct all the
data for availability control. The assigned values are recalculated and
references are created to the objects that have budget.
The new budget profile settings are copied into the budget table.
Recommendation
SAP recommends that you reconstruct
the
PS
Info Database with transaction CJEN before activating
availability control
Activities
Carry out this step if:
1. you install
a new release
2. you haved
changed the availability control settings in the budget profile (e.g. from
overall to annual values)
3. you have
changes the tolerance limits for availability control
4. you have
defined exempt cost elements - that is, cost elements which are not subject to
availability control
5. you have
changed the order update settings for orders for projects
6. you suspect
errors in the data - for example, in objects from older releases or after
incorporating corrections relating to budgeting or availability
control