Project Cost Forecast 

Description

As a project is executed, variances occur between planning and the actual costs incurred. To achieve a realistic cost forecast, you need to use the existing data as a basis for projecting how costs will develop until the project is complete. From Release 4.5A, you can use the calculated plan costs (plan version 000) to determine the estimate to completion and estimate at completion for activities and material components in collective stock. Costs already incurred (actual and commitment) are included. The values generated automatically are editable. You can enter more values manually in cost element planning for WBS elements. This gives you a solid basis for your cost forecast.

The updated residual costs are stored in their own plan version, along with the actual and commitment values; you can evaluate them in the information system. You can create more than one version. In the standard, we deliver CO plan version 110 for the exclusive use of forecast costs.

Forecast values are only determined for activity-assigned networks which are both additive and apportioned.

The following are not considered as the forecast is calculated:

Determining the Updated Residual Costs

The basis for the updated residual costs are the calculated planl costs for activities. Overhead is automatically included in the determination. Below are details of how the various activity types are treated.

Internally-processed activity

Externally-processed activity

General costs activity

Material component

Plan costs for material components in valuated project stock are not included in the calculation of updated residual costs at this time.

The actual and commitment values arising from deliveries, confirmations, or usage of the component in the WBS element or activity are included in the calculation of the updated overall costs.

Changes to the interface

To access the forecast run, go to the Project Execution menu and choose Period-end closing -> Cost forecast -> Individual processing or Collective processing.

Changes in procedure

Forecast values are usually determined as part of period-end closing. Before the forecast run, you must carry out the following:

Once the forecast run has taken place, you can change the forecast values manually.

Further notes

We deliver the hierarchy report 12ctc1 Forecast as standard, so that you can evaluate forecast values and compare them with the plan, actual, and commitment values for any CO version you want.