Stock Transfer from Plant to MRP Area 

Description

You use this function if you work with MRP areas in material requirements planning and would like to procure a material for an MRP area by transferring stock from the plant.

If you would like to plan material requirements for a storage location separately, you can create an MRP area for this storage location. You can then procure materials that are planned for this MRP area via stock transfer from plant to MRP area.

If you plan components to be provided for a subcontractor using an MRP area of the subcontractor type, you can also procure the components to be provided via stock transfer from the plant to the MRP area.

Prerequisites

Features

During the planning run, the system creates a stock transfer reservation for the material in the MRP area and a material reservation for the material in the plant MRP area. The external procurement storage location that you have entered in the MRP area segment of the material master is used as the receiving storage location.

The actual procurement is processed by the plant. With stock transfer to the MRP area, you carry out the transfer posting for the material with reference to the reservation.