If you carry out planning for the components to be provided to a subcontractor with an MRP area for this subcontractor and the components to be provided are procured externally, you can process the procurement of these components using subcontracting/third-party order.
This type of processing has the advantage that the required components to be provided are delivered directly from the vendor, from whom you order this material, to the subcontractor.
In the planning run, the system creates a planned order or a purchase requisition for the components to be provided that are required by the subcontractor. The planned order or the purchase requisition already contain the subcontractor's delivery address, that is, the address of the subcontractor is displayed, to which the components to be provided are to be delivered.