Show TOC
Planned cost
calculation
Definition
Determines whether
planned costs are automatically calculated when
you save the network.
The following options exist:
- 0: No planned costs are calculated when
saving
- 1: Planned costs are calculated when saving,
if the network has been released.
Planned costs are
only calculated if the network header has the status
REL.
- 2: Planned costs are calculated when
saving.
Dependencies
If you specify that no planned costs are
calculated when you save, you can trigger planned costs calculation at any
time from the order.