In this list field, you can choose one of the following variants for inspection point completion:
The valuation screen for the inspection point is either called up automatically after the inspection characteristics have been closed when you exit the characteristic overview screen, or you can call up the screen manually using the function key.
You must assign a quantity and valuation to the
inspection point.
Depending on the control key used for the operation, the system suggests a
confirmation indicator (for example, partial confirmation, final confirmation,
or "no confirmation" for the order)
The valuation screen for the inspection point is called up automatically after the inspection characteristics have been closed, or you can call up the screen manually using the function key.
You must assign a quantity and valuation to the
inspection point.
The confirmation indicator is set to "No confirmation". However, you can
activate the confirmation despite this setting if you have set the control key
accordingly.
The valuation screen for the inspection point is called up automatically after the inspection characteristics have been closed, or you can call up the screen manually using the function key.
You must only assign a valuation to the inspection point.
The valuation screen for the inspection point is not called up after the inspection characteristics have been closed.
The inspection point is valuated automatically using the inspection point definition.
Note
The valuation screen is always called up, if you:
Assign the relevant variants to the inspections: