earned value

Project System (PS)

Value of the services actually performed in a project.

The term "earned value" describes the costs incurred in bringing a project element to its current degree of completion.

To calculate the earned value, the system usually multiplies the degree of completion by a planning factor, such as the original plan or the budget.