With Release 3.0E the project hierarchy of work breakdown structures, networks and other orders such as production orders, internal orders etc.) is displayed in the project information system according to the following “rules”:
In all other cases, the hierarchy will be displayed as demonstrated in the following example:
PD=Project definition, NW=Network, ACT=Activity, WBS=WBS element
| Objects | Assignment |
| PD-A | |
| WBS-A1.1 | PD-A |
| WBS-A2.1 | PD-A |
| WBS-A3.1 | PD-A |
| NW-1 | PD-A and WBS-A2.1 |
| NW-2 | PD-A |
| NW-2ACT-2 | |
| NW-3 | |
| NW-4 | PD-B |
| NW-4ACT-4 | WBS-A3.1 |
In the project information system: structure/dates the hierarchy is displayed as shown below:
Level
0 PD-A
1 WBS-A1.1
2 WBS-A2.1
3 NW-1
2 WBS-A3.1
3 ACT-4
1 NW-2
0 ACT-2
0 NW-3
0 NW-4