Material components in networks: Enhancements in
Release 3.0E
Description
In Release 3.0E the following enhancements have been made to the
functionality of material components in networks:
- multi-level bill of material explosion
You can now explode a BOM in a network and see
all levels. Set the indicator multi-level explosion
to do this. If you don't set the indicator, only the first level of the bill
of material will be shown.
- manual entry of requirements dates
You can now view the requirements date of the
material components on the purchasing detail screen. You can also enter a
requirements date manually on the detail screens. In addition, you can
determine that the requirements date is not automatically copied from the
network activity date by setting the indicator
ManRqmtDte . When you set this indicator, this component will
not be included in scheduling, which means that its requirements date will be
independent of the activity dates.
The system will now propose a unique ascending
number for the component item number in network activities. In addition, you
can renumber the item numbers in each activity. Do this select the menu
options Edit -> Renumber item no..