Select Fields in the Tree 

Use

You can define which fields are shown in the material tree and in which sequence they are arranged.

You can carry out the definition of the fields and their sequence, independently of each other, in the following applications:

Prerequisites

Procedure

  1. Choose .
  2. The system displays the Define fields and sequence dialog box.

  3. Enter a sequence number next to each field that you want to be displayed in the tree.
  4. You want to display the Processed MRP lists, Traffic light, Material, MRP area, Material description fields in this sequence. Enter:

    Processed MRP lists

    1

    Traffic light

    2

    Material

    3

    MRP area

    4

    Material description

    5

    You want to change the defined sequence so that the traffic light is first. Enter the following change:

    Traffic light

    1

    The remaining fields are resorted automatically when you confirm the entry with Enter.

  5. Choose Copy settings to activate the settings for the current display, or to save them permanently.

Result

The system displays the selected fields in the defined sequence in the material tree.

You can change the sequence of the fields in the current display by moving the relevant column header to a new position using the mouse.