Use
You first have to activate adjustment runs so that the adjustment amounts calculated for the condition types are updated in the corresponding rental units or lease-outs.
The debit position only takes account of the new amounts on the date specified once the adjustment has been activated; however you can still change the adjustment amounts in any of the objects.
Prerequisites
You have an adjustment run (user identification).
Procedure
You have the following options in the selection screen:
Options |
Procedure |
You do not want to activate all rent adjustments of one adjustment run (User-ID(s) or Valid from date) |
Select the lease-outs or rental units for which you want to activate the rent adjustment in the Business entity, Rental unit, Lease-out fields Example Rent Adjustment: Selection Options For Activating |
You want to have adjustments done for lease-outs once the tenant has approved |
Set the indicator in the Selection acc. to category and status group box |
You want to directly release all subject-to-approval adjustments of a lease-out selection for activation |
Enter the required date in the Approval date proposal field This date is copied to the selected adjustments but can still be manually changed Otherwise you have to add the approval date to each individual subject-to-approval adjustment for a lease-out to be able to activate them |
You want to activate directly all adjustments of an object selection |
Enter the required date in the Approval date proposal field and flag the Activate directly? field |

Result
If you have selected the Activate directly? field, the system activates the adjustment and updates the respective lease-outs or rental units as new condition items.
If you have not selected the Activate directly? field, you get a list of adjustments for further editing:
Action |
Choose |
Edit adjustment (change amount, enter approval/rejection) |
The required adjustment and then Detail |
Reset all selections or reselect all adjustments |
Deselect all or Select all function (for adjustments subject to approval, the lease-outs selected are only those for which an approval date has been entered) |
Do not carry out activation |
Back |
Activate all selected adjustments |
Activate The adjustment is thus copied to the respective lease-outs or rental units as a new condition item with the specified date |