Planning in the Implementation Phase 

Use

There are two possible objects that can be used for planning appropriation requests that have already been transferred to measures for their implementation:

Usually it is most practical to carry out planning during the implementation phase on the measure itself. However, in some enterprises, investment planning is conducted centrally in the organization, whereas the measures are managed in decentralized organizational units during their implementation. In this case, the appropriation request then serves as the central object for planning and updating the plan, both in the approval phase and in the implementation phase.

Features

You specify in the appropriation request type where planning and plan updates should take place (Customizing: Control Data). You specify that planning should be done either:

As long as the appropriation request is not released, you have to enter plan values in the appropriation request in any case.

Planning in the Measure

If you have stipulated planning in the measure during the implementation phase, the system automatically sets Replaced by measure status when the appropriation request is released. The results are as follows:

Planning in the Appropriation Request

You should keep the following points in mind, if you continue to use the appropriation request for planning during the implementation phase: