Changing the Material Master Record 

  1. Call up the transaction as follows:
  2. Menu Path

    Logistics ® Materials Management ® Material Master ® Material ® Change ® Immediately

    Transaction Code

    MM02

  3. Enter the following data:
  4. Field

    Data

    Material

    AM2-GT

  5. Choose Select view(s).
  6. In the dialog box, choose .
  7. Select the line MRP4.
  8. Choose Organizational levels.
  9. In the Organizational Levels dialog box, enter the following data:
  10. Field

    Data

    Plant

    1000

  11. Choose .
  12. Check the entries in the screen Change Material AM2-GT (Finished product) and change them as necessary:
  13. Field

    Data

    Repetitive manufacturing

    Select

    REM profile

    A002

  14. Choose .
  15. You receive the message Material AM2-GT changed (if relevant).

  16. Choose .