Executing Multi-Level Requirements Planning 
Menu Path |
From the Production node, choose MRP ® Planning ® Single Item, Multi-Level |
Transaction Code |
MD02 |
Field |
Data |
Material |
T-MV |
Plant |
1000 |
Processing key |
NETCH |
Create purchase req. |
3 |
Delivery schedules |
1 |
Create MRP list |
1 |
Planning mode |
3 |
Scheduling |
1 |
Also plan unchanged components |
Select |
Display material list |
Select |
.To ignore any warning messages, choose
.
The statistics overview appears.
You see the planning results based on the planned orders generated during MRP for the finished product.
A dialog box appears.
You can analyze more materials or planned orders of the dependent requirements on this screen.
In the dialog box, choose Yes.