Settings for External SOP Planning 
Use
To use the SOP external planning functions, you must maintain the settings in the sttings for External SOP Planning window. This window pops up each time you begin planning externally, and is divided into four planning sections:
Structure
Planning Control
The following flags can be set under planning control in the Settings for External Planning screen:
The external planning action controls the planning process in the external system.
Single planning: Set flag for single planning, otherwise all the materials and product groups could be affected.
Plan initialization flag: If you set this flag, the entire plan is erased before new values are entered and the plan is created again from scratch. You should only set this flag in case an error has already occurred in the plan and you want to correct it.
Planning Features
In this section of the window, Use Material Availability, you must select one of the following options to indicate if the current material availability status should be transferred from R/3 to the external planning system:
Planning Strategy:
This section of the window is activated only when planning a disaggregated product group. Select one of the following to indicate planning strategy.

Use the same strategy throughout the entire version of your plan, otherwise materials or product groups may be planned twice. Be careful not to plan production and demand figures for multiple levels of the same product group in a planning version by accident.
Planning Target:
Keep in mind that four lines (sales, production, target stock levels, and target day’s supply) from the standard SOP rough-cut planning profile are always transferred to the external system, but not all four must be used for external planning.
If your planning target is |
the external system processes |
production figures |
sales and production figures |
synchronous to sales |
only sales figures |
target stock level |
sales figures and target stock levels |
target day’s supply |
sales figures and target day’s supply |
stock level - zero |
sales figures and opening stock levels |

If you select stock level - zero, also set ‘Use opening stock levels’ flag