CLOI_PLORD_OPRU_IMP 

This table is used if in planned orders are to be changed.

CLOIPLOPRU

Field

Description

Type

Length

PLNUM

Planned order number

char

10

EXTPLNUM

External planned order number

char

10

PLNFL

Sequence number

char

6

VORNR

Operation number

char

4

<FIELD>

Field name of a planned order

char

10

<VALUE>

Value of the field

char

50

 

The following fields are possible:

<FIELD>

Description

Type

Length

ARBPL

Key identifying the work center

char

8

WERKS

Key identifying a specific plant

char

4

ARBID

This internal number, together with the object type, identifies the operating resource, such as the work center or production resources/tools.

numc

8

VGW01

Standard value

char

10

VGE01

Unit of the standard value

char

3

VGW02

Standard value

char

10

VGE02

Unit of the standard value

char

3

VGW03

Standard value

char

10

VGE03

Unit of the standard value

char

3

VGW04

Standard value

char

10

VGE04

Unit of the standard value

char

3

VGW05

Standard value

char

10

VGE05

Unit of the standard value

char

3

VGW06

Standard value

char

10

VGE06

Unit of the standard value

char

3

USR04

User-defined field for quantity

char

15

USE04

User-defined field for the unit of the quantity field

char

3

USR05

User-defined field for quantity

char

15

USE05

User-defined field for the unit of the quantity field

char

3

BMSCH

Base quantity

char

14

FSEDD

Earliest date when execution of the operation can finish

dats

8

FSEDZ

Earliest time when execution of the operation can finish

tims

6

FSAVD

Earliest date when execution of the operation can start

dats

8

FSAVZ

Earliest time when execution of the operation can start

tims

6

FSSBD

Earliest date when processing of the operation can start

dats

8

FSSBZ

Earliest time when processing of the operation can start

tims

6

FSSAD

Earliest date when teardown of the operation can start

dats

8

FSSAZ

Earliest time when teardown of the operation can start

tims

6

SSEDD

Latest date when execution of the operation can finish

dats

8

SSEDZ

Latest time when execution of the operation can finish

tims

6

SSAVD

Latest date when execution of the operation can start

dats

8

SSAVZ

Latest time when execution of the operation can start

tims

6

SSSAD

Latest date when teardown of the operation can start

dats

8

SSSAZ

Latest time when teardown of the operation can start

tims

6

SSSBD

Latest date when processing of the operation can start

dats

8

SSSBZ

Latest time when processing of the operation can start

tims

6

METHOD

Methods are functions that can be carried out for only one object. Example: scheduling orders

Possible values:

Dispatch:

Dispatching operations (status "dispatched" is set after the data changes are made in the operation and the operation is rescheduled, if necessary)

Deallocate:

Deallocate operations (status "deallocated" is removed)

char

50

EXTPLNUM is only used for planned orders that were created by the optimization program. Since the external system does not recognize the SAP planned order number, the optimization system creates one of its own.

Always enter the date and time in the specified format.

You can enter the date and time for an operation in two ways:

If you enter the date and time and choose Dispatch as the method, the R/3 System no longer changes the times when scheduling.

Scheduling-related changes in the planned order automatically trigger deallocation.

You can define the work center either using the field ARBID or the fields ARBPL and WERKS.