This table is used if in planned orders are to be changed.
CLOIPLOPRU
Field |
Description |
Type |
Length |
PLNUM |
Planned order number |
char |
10 |
EXTPLNUM |
External planned order number |
char |
10 |
PLNFL |
Sequence number |
char |
6 |
VORNR |
Operation number |
char |
4 |
<FIELD> |
Field name of a planned order |
char |
10 |
<VALUE> |
Value of the field |
char |
50 |
The following fields are possible:
<FIELD> |
Description |
Type |
Length |
ARBPL |
Key identifying the work center |
char |
8 |
WERKS |
Key identifying a specific plant |
char |
4 |
ARBID |
This internal number, together with the object type, identifies the operating resource, such as the work center or production resources/tools. |
numc |
8 |
VGW01 |
Standard value |
char |
10 |
VGE01 |
Unit of the standard value |
char |
3 |
VGW02 |
Standard value |
char |
10 |
VGE02 |
Unit of the standard value |
char |
3 |
VGW03 |
Standard value |
char |
10 |
VGE03 |
Unit of the standard value |
char |
3 |
VGW04 |
Standard value |
char |
10 |
VGE04 |
Unit of the standard value |
char |
3 |
VGW05 |
Standard value |
char |
10 |
VGE05 |
Unit of the standard value |
char |
3 |
VGW06 |
Standard value |
char |
10 |
VGE06 |
Unit of the standard value |
char |
3 |
USR04 |
User-defined field for quantity |
char |
15 |
USE04 |
User-defined field for the unit of the quantity field |
char |
3 |
USR05 |
User-defined field for quantity |
char |
15 |
USE05 |
User-defined field for the unit of the quantity field |
char |
3 |
BMSCH |
Base quantity |
char |
14 |
FSEDD |
Earliest date when execution of the operation can finish |
dats |
8 |
FSEDZ |
Earliest time when execution of the operation can finish |
tims |
6 |
FSAVD |
Earliest date when execution of the operation can start |
dats |
8 |
FSAVZ |
Earliest time when execution of the operation can start |
tims |
6 |
FSSBD |
Earliest date when processing of the operation can start |
dats |
8 |
FSSBZ |
Earliest time when processing of the operation can start |
tims |
6 |
FSSAD |
Earliest date when teardown of the operation can start |
dats |
8 |
FSSAZ |
Earliest time when teardown of the operation can start |
tims |
6 |
SSEDD |
Latest date when execution of the operation can finish |
dats |
8 |
SSEDZ |
Latest time when execution of the operation can finish |
tims |
6 |
SSAVD |
Latest date when execution of the operation can start |
dats |
8 |
SSAVZ |
Latest time when execution of the operation can start |
tims |
6 |
SSSAD |
Latest date when teardown of the operation can start |
dats |
8 |
SSSAZ |
Latest time when teardown of the operation can start |
tims |
6 |
SSSBD |
Latest date when processing of the operation can start |
dats |
8 |
SSSBZ |
Latest time when processing of the operation can start |
tims |
6 |
METHOD |
Methods are functions that can be carried out for only one object. Example: scheduling orders Possible values: Dispatch: Dispatching operations (status "dispatched" is set after the data changes are made in the operation and the operation is rescheduled, if necessary) Deallocate: Deallocate operations (status "deallocated" is removed) |
char |
50 |

EXTPLNUM is only used for planned orders that were created by the optimization program. Since the external system does not recognize the SAP planned order number, the optimization system creates one of its own.
Always enter the date and time in the specified format.
You can enter the date and time for an operation in two ways:
If you enter the date and time and choose Dispatch as the method, the R/3 System no longer changes the times when scheduling.
Scheduling-related changes in the planned order automatically trigger deallocation.
You can define the work center either using the field ARBID or the fields ARBPL and WERKS.