CLOI_PLORDU_IMP 

This table is used if planned orders are to be changed (updated) in the R/3 System.

CLOI_PLORDU_IMP

Field

Description

Type

Length

PLNUM

Planned order number (in SAP System)

char

10

<FIELD>

Field name of a planned order

char

10

<VALUE>

Value of the field

char

50

 

The following fields are possible:

<FIELD>

Description

Type

Length

PWWRK

Number of the plant where the order quantity of the material is produced in-house

char

4

BDMNG

Quantity of the material component

char

14

AVMNG

Scrap quantity forecast

dats

8

PSTTR

Earliest date when production starts according to the planned order

dats

8

PEDTR

Date when the planned order quantity is expected to be available or delivered according to the planned order

dats

8

GSTRS

Scheduled start date

dats

8

GSUZS

Scheduled start time

tims

6

GLTRS

Scheduled finish date

dats

8

GLUZS

Scheduled finish time

tims

6

VERID

Production version

char

4

SEQNR

Sequence number

numc

14

SERNR

Serial number to which a fixed key date can be assigned. This specifies a date for the production series that is used to determine the valid bill of material or routing

char

8

UMSKZ

Initial value only.
Set on empty for BOM production or repetitive manufacturing

   

MDACC

Key describing one of the actions listed below that can be carried out for a planned order

- RSMNA: reset material availability

- BOME: explode bill of material

- BEMA: explode bill of material and check material availability

- MAAV: check material availability, explode bill of material, if necessary

- NEMA: check material availability without exploding bill of material

- SCHE: schedule planned order

- Customer-defined actions. See last note below.

char

4

 

With scheduling-related changes:

The scheduling type is specified in Customizing.

With changes to the production version: the routing and bill of material are exploded and the order is rescheduled (according to the Customizing settings).

If you enter a production version, the planned order is assigned to the corresponding run schedule header.

A planned order is fixed once it has been created, which means that planned orders cannot be changed automatically in the R/3 System.

You can use the interface to change or delete fixed planned orders.

You must enter the date and time in the predefined format.

The customer-defined action key and the action management can both be maintained in Customizing. Follow this path in the customizing menu. Production ® Material requirements planning ® Procurement proposal ® Planned orders ® Action in planned order ®

Scheduling begins at time/date transferred in GSTRS/GSUZS or GLTRS/GLUZS. However, PSTTR or PEDTR are also transferred since they are mandatory fields. The required scheduling direction determines which fields are used.

In order to enable scheduling with times, the following scheduling types must be defined in Cutomizing,(IMG ® Production ® Capacity Requirements Planning ® Operations ® Scheduling ® Specify scheduling type):

5 = Forward scheduling

6= Backward scheduling