Availability Check and Transfer of Requirements

Depending on the system configuration, the SAP System can check availability for every item in a document or delivery. Furthermore, it creates MRP records and passes them on to materials planning. The availbility check is carried out at plant level.

Control elements in Customizing

In addition to other settings, the following control elements are of particular signifiance in SD-Customizing:

The checking rule determines the scope of the availability check and whether or not the replenishment lead time should be taken into account.

The MRP groups are defined in materials planning in PP Customizing.

Note

The control of the check's scope and the type of requirements records are interdependent.

Specifications in the material master record

You make two particularly significant specifications in the material master record for the availability check and transfer of requirements:

The following further control elements in the material master record can also influence the result of the availability check:

Further possibilities for controlling the availability check and transfer of requirements

The availability check and transfer of requirements can in principle be controlled independently of one another.

When you create a sales document, the transfer of requirements and availability check can be carried out independently. The way in which these are controlled is dependent on th requirements class and schedule line category.

When you create a delivery, the availability check can only be carried out in combination with the transfer of requirements. Requirements, however, can be transferred without the availability check being carried out.

These control elements apply to sales documents and deliveries alike. The procedure and scope of the check can, however, be controlled separately for sales documents and deliveries, so that a different type of availability check is carried out in delivery processing as in sales order processing, for example. In sales documents, you can block order quantity confirmation (for certain delivery blocks), for instance.

Further literature

1. For a detailed description of the availability check and transfer of requirements from the point of view of the user, see the SD Sales and SD Shipping manuals.
2. The PP Master Planning/MRP Guide describes the determination of the requirements type.
3. For further information on the MRP group, see IMG step "Planning strategy" for materials planning. The MRP groups are configured under the menu option " Master data " in materials planning in Production. Requirements type determination is also to be found here.