Show TOC

Parallel valuation using the costing key

Description

The costing key specifies the key parameters with which the system accesses a product cost estimate.

You can assign up to three cost estimates to a product and/or material type either by activity or for a specific point of valuation. This makes it possible to valuate using up to three cost estimates at the same time.

The assignment of cost components to value fields is dependent on the point of valuation.

Each component can be assigned to up to three value fields -- corresponding to the assignemnt of cost estimates to products or material types.

Change system parameters in customizing

Define costing key

Assign costing key to products

Assign costing key to material types

Assign cost components to CO-PA fields