Define Control Parameters for Completion Confirmations

In this work step, you maintain the control parameters for completion confirmations in maintenance orders.

You can set control parameters for each order type.

Using the completion parameters, you define:

To do this, you can proceed as follows:

You can propose that completion confirmation data which is still open be entered. For the activities, the SAP System then proposes the difference between the the specifications and the values already confirmed. Otherwise, the default values are proposed each time as completion confirmation data.
For information, you can display both the data already confirmed and the specifications.
Here you can define whether a partial completion confirmation, a final completion confirmation or a final completion confirmation with charging of open reservations should be proposed.
Here you can define whether the actual work should be calculated automatically (taking into account the remaining work and the final completion confirmation indicator).
You have confirmed the following values for an operation:
Confrmtn Plnd work Act. work Rem. work Final confrmtn
1) 10 6 4
2) 10 X
If the indicator 'Calculate activities' is set, 4 hours (the remaining work) is saved, if the indicator final completion confirmation is set.
If the indicator is not set, the operation is finally confirmed for single entry of the final confirmation indicator, but no actual work is saved.
You can use the inspections to define:
The features of the control key Process control are defined in another place in Customizing. It controls the execution of the completion confirmation processes.
You can use the indicator All components to specify that all components which are assigned to the operation (this means not only retrograde components) are displayed in the overview of the goods movements. However, if you do not branch to the material overview for the completion confirmation, then only retrograde components continue to be withdrawn.
Under selection, you define that for the implementation of completion confirmation processes
You can use the indicator Actual costs to define that the log is also displayed if there are no error messages (only warning messages or information messages) available.
You can use the indicator Goods movements to specify that an error log is displayed for incorrect items of the goods movements (for retrograde/unplanned withdrawals). Consequently, you can improve the items again before saving using the material overview.
You can use the indicator No HR update to activate the decoupling between HR and PM.

Activities

Define the parameter settings for the completion confirmations in your plant for the possible order types.