Define Confirmation Parameters

In this step, you define the confirmation parameters for each plant and order type. The parameters are split up as follows on tab pages (for information on the validity of the parameters, refer to

Further Notes

)

Generally valid settings

Using checks you can define
You can choose between a termination message, an error message, a warning message and an information message.
You can decouple HR and PP with the No HR update indicator.
You specify that only open orders are selected in the collective order.
You can select a time unit that is to be proposed during confirmation.
Using the all components indicator, you can specify that the system should display all the components assigned to the operation in the goods movement overview (in other words, not only backflushed components). However, if you do not branch to the material overview at confirmation, the system only posts backflushed components.

General individual entry

You can define here whether a partial confirmation, a final confirmation or a final confirmation with clearing of open reservations is to be proposed for the confirmation.
You can use the indicator Actual costs to specify that the log is also displayed if there are no error messages (thus only warnings or information messages).
You can use the Error handling indicator to specify that an error log is displayed for incorrect items in goods movements (for backflush or automatic goods receipts). You then have another opportunity to correct the items with errors before saving, with the aid of the material overview.

Individual operation entry with the initial screen

You can have the system propose the open confirmation data for entry. For the quantities and activities, the SAP System proposes the difference between the standard values and the confirmed values. Otherwise, the standard values are proposed as confirmation data.
You can have the system display both the confirmed data and the standard values for information purposes.
If you do not select an entry screen on the initial screen, you can control the following alternative entry screens by parameterization:
You define that confirmable or confirmed operations are also selected during the execution of the confirmation processes

Activities

Define the parameter settings for the confirmations in your plant for the possible order types.

Further Notes

For information about the validity of IMG activities relating to the transactions for confirmation entry, refer to Validity of IMG Activities for Confirmation .