Converting the Planned Order into a Production Order 
On the Stock/Requirements List as of ## Hrs screen, double-click on your planned order to the display detailed information.
A dialog box appears.
Choose -> Prod. Order (Convert planned order into production order).Choose
.
You see the material components.
Choose
.
Choose
.
You now see the operations.
Make a note of the final operation in the list (0060).
To analyze the operations schedule, choose Goto
®
Graphic
®
Gantt chart.
Choose
.
In the dialog box, choose Yes.
Choose
.
To schedule the order, choose
.
Choose
.
Make a note of the production order number.
Choose
.
The planned order (PlOrd.) was converted into a production order (ProdOrd).
Choose
until the overview tree appears.