Copying Actual Data to the Reference Version 

Purpose

To make the data from 1999 available for the reference version for 2000, you copy the actual data to the reference version.

Procedure

  1. Call up the transaction as follows:
  2. Menu Path

    Accounting ® Controlling ® Profitability Analysis ® Planning ® Edit Planning Data

    Transaction Code

    KEPM

  3. Choose in front of planning level IDES 140.
  4. Two planning packages appear.

  5. Double-click planning package IDES 140.
  6. On the right side of the screen, you see the characters chosen for this planning level, including the characteristic values determining the characteristic combination. The reference data is thus to be copied to these characteristics.

  7. In the planning methods area (bottom left), choose IDES 140 ® Copy.
  8. Double-click parameter set IDES 140.
  9. The system now copies the reference data.

  10. Remain on this screen.