Customizing for Setting Up Ratios 
Use
The following steps let you look at the Customizing settings that need to be made in order for you to use ratios and ratio schemes in planning. You do not need to change these settings.
Procedure
Menu Path |
Tools ® AcceleratedSAP ® Customizing ® Edit Projects. |
Transaction Code |
SPRO; KE1L |
Menu Path |
Controlling ® Profitability Analysis ® Planning ® Planning Aids ® |
Transaction Code |
KE1I |
Field |
Data |
Operating concern |
IDEA |
Type of Profit. Analysis |
costing-based |
You see the ratios that have been defined thus far.
The ratio ERL represents the formula "revenue divided by sales quantity". Value field VV010 (revenue) is the numerator and value field VVIQT (invoiced quantity) is the denominator. The ratio ES represents the sales deductions, while HK shows the cost of goods manufactured.
These ratios are defined as follows:
Sales revenue / Quantity = Price per unit
Customer discount / Quantity = Sales deductions per unit
Cost of goods mfd / Quantity = Cost of goods mfd per unit
These ratios must be assigned to access-level characteristics, which define the level at which the values should be stored (the sales organization, customer, and product, in this example).
The three ratios with a "1" on the end represent the same as the above three ratios, except that they are assigned to the access-level characteristics "Sales organization" and "Material group". Prices are calculated as the average prices at the material group level instead of per customer and product in one sales organization.
You see that various schemes have already been defined. Scheme PPDB defines the prices at the customer/product level, while scheme PPDG defines them at the material group level.
You see the ratios that have been assigned to this scheme.
The System shows you the levels at which these ratios are to be calculated.