Availability Control: New Developments in
3.0
Description
- Deactivating availability control
From Release 3.0, it is possible to deactivate
availability control, once it is activated, for one or more projects.
You might want to do this, for example, if
- you activated availability control accidentally
- in availability control based on the annual budget, availability control
was active in the previous year, but it is, as yet, too early in the current
year for availability control to be of practical use.
The activity groups of the budget availability
control were enhanced by:
- Fixed prices in the project
- Funds reservation (manual commitment)
In the budget profile, you can determine whether
the availability control is checked against
Additional information