Change in Progress Confirmation
Scope of Functions
During progress confirmation, a distinction is no longer made between
whether or not a confirmed operation is a planned milestone. A manually confirmed operation is always identified in the same way:
- All operations receive the operation status PROG (progress confirmation)
- When a confirmation is entered manually, the field MILE (milestone
confirmation executed) is set to the following value: "D - dynamic milestone"
- For the operations that precede the manually entered operation, the