Ordering an Item from One-Time Vendor who Quoted Lowest Price 
Menu Path |
From the Materials Management node, choose Purchasing ® Purchase Order ® Create ® Vendor/Supplying Plant Known |
Transaction Code |
ME21N, ME53N |
Field |
Data |
|
Standard PO |
, next to
.
.All RFQ numbers found for vendor 1950 are now listed in the purchasing document overview.
from the document overview area.
.
.
.
.
If the
icon should not be visible, enlarge the Document Overview area accordingly.
The RFQ item is adopted in the purchase order and listed in the item overview. In the RFQ field of the item, you again find the RFQ number you chose.
Item details. Field |
Data |
Material |
R-1150 |
PO quantity |
100 |
C (Category of delivery date) |
D |
Delivery date |
Four weeks from today |
Net price |
Previously entered net price |
Plant |
1200 |
Storage location |
0001 |
.
Header.
.
The system confirms that a purchase order has been created under the number indicated. Note this number.
until the overview tree appears.You now have the opportunity of displaying the ordering status of the underlying requisition.
Menu Path |
From the Purchase Requisition node, choose Display. |
Transaction Code |
ME53N |
.
Item detail.On the tab page Status you will see the purchase order and its number assigned to material R-1150.