Executing Order Split 

Prerequisites

An order that you want to split must meet certain prerequisites (see Prerequisites).

Procedure

  1. Choose Logistics ® Production ® Shop floor control ® Order ® Change.
  2. Enter the order number.
  3. Choose .
  4. The operation overview of the standard sequence appears.

  5. Select the operation from which you want to split the order.
  6. The operation from which you want to split the order (the split operation) must be an operation of the standard sequence.

  7. Choose Functions ® Split order.

If serial numbers already exist for the order, the system asks you to select the serial numbers that you want to use in the child order.

If the order has parallel sequences, and at least one sequence is parallel to the split operation, the system asks you to select the operations of the parallel sequences that are to participate in the order split. The system displays the affected parallel sequences for selection one after the other. You have the following selection options:

  1. Enter the Split quantity.
  2. The entire operation quantity is not available as the split quantity (see Order Split).

    If necessary, you can also enter the Order type and Order number (in the case of external number assignment), as well as the scheduling data.

  3. Choose Split order.
  4. Choose .

Result

A new child order has been created. In the split hierarchy, this child order is subordinate to the parent order from which it was split.