System Status in Standard Work Breakdown Structures 

Standard WBS elements do not have their own status. The status of the standard project definition is valid for all WBS elements.

Released (REL)

Use

You use this status to activate standard work breakdown structures. If a standard work breakdown structure has Released status, you can use it as a template for creating work breakdown structures.

Prerequisites

Released status can be set after Created status.

Features

In this status you can change the structure.

You cannot cancel the status.

Closed (CLSD)

Use

You use this status to indicate that a standard work breakdown structure is no longer required.

Prerequisites

You can only set the Closed status after Released status.

The Technically completed status does not exist for standard work breakdown structures.