Material Management in the Project Planning Board 
Use
You use the functions described here to manage your project material components directly in the project planning board.
Features
Gantt Chart
In the Gantt chart you can carry out the following functions. These functions refer to a selected WBS element or network activity. It is not possible to select individual components in the Gantt chart. To do this, call up the component overview.
Function |
Menu Path |
Comments |
Create component assignments |
Edit ® Create... |
See
Creating Project Objects |
Check material availability for the network |
Edit ® Functions ® Material availability (network) |
Carries out a material availability check for all the components in the network assigned to the selected WBS element. See also: Material Availability Check. |
Activate purchase requisition/reservation |
Edit ® Functions ® Activate Purc Req/Res. |
Irrespective of the settings in the component detail screen, you can use this function to manually create purchase requisitions or reservations for a WBS element. See also: Activating Requirements. |
Component Overview
Several more functions, for individual components, are available from the component overview. Apart from detail screen, which can also be called up by double-clicking on the component, all functions are called up from the context menu.
Function/Menu Entry |
Comment |
Available quantity |
The system displays the component availability as a bar chart in the component overview. |
Availability check |
An availability check is carried out for the selected component. For more information, see Material Availability Check. |
Detail screen |
Opens the component detail screen for the selected component. For more information, see The Component Detail Screen. |
GR/GI list |
A further window opens with procurement details, such as document (purchase requistions or reservations etc) details and details of goods movements etc. |
Explode BOM |
If the selected component has a bill of material, this is exploded, either level-by level or the whole structure (multi-level). For more information, see Exploding the Bill of Material. |
Dates overview |
If you have maintained the requisite settings in Customizing for Monitoring Dates, the systems displays the dates overview. |
Reassign |
You use this function to reassign a component from one activity to another in the same network. |
Create document |
You can create a document (document info record and if necessary original application file) that is assigned to the component Be sure to a document type that can be assigned to a material component. For more information, see
Document. |
Document overview |
Provides an overview of documents assigned to the component. |
Delete |
Deletes the component assignment, if this is allowed, that is if there are no open procurement documents such as purchase requisitions or reservations for the component. |