Prerequisites
You are in a project in the project planning board or the Project Builder.
You can only confirm activities and activity elements, if
You must have defined certain confirmation parameters in Customizing for the Project System previously.
For more information, see
Confirmation Directly in the Project System.
Procedure
Choose in the |
Pushbutton/Menu Path |
Project Builder |
Edit -> Activity -> Confirm |
Project planning board |
|
The Create Network Confirmation: Actual Data screen appears.

Before you leave the confirmation, you can go to a separate dialog box to enter goods movements.
Result
According to your settings in Customizing, the system executes the confirmation immediately or later in a background job.