Routings (PP-BD-RTG) 

Purpose

Routings enable you to plan the production of materials (products). Therefore, routings are used as a template for production orders and run schedules as well as as a basis for product costing.

Integration

In order to

You also require the components

Plan the usage of materials

Material master (LO-MD-MM)

Plan the use of work centers

Work centers (PP-BD-WKC)

Plan the external processing of operations

Purchasing (MM-PUR)

To plan quality inspections that accompany production

Quality planning (QM-PT)

To prepare cost calculation according to routings

Controlling (CO)

To plan and to document changes to routings

Engineering Change Management (LO-ECH)

To classify routings

Classification system (CA-CL)

To automatically calculate the planned values for the activities to be produced

CAPP Standard Value Calculation (PP-BD-CAP)

In the R/3 System, routings have the same basic structure as the following objects:

Therefore, routings are cumulated with these objects under the superordinate term Task list.

Features

In a routing you plan